Casinos are constantly remodeling, revising and updating. Because they are open for business twenty four hours a day, seven days a week, these projects present logistical challenges.
Imagine remodeling the front entrance and lobby of one of the busiest hotels in the world, never closing the doors, and never disrupting a customer. This was Superior’s challenge, and its success, on the Caesar’s Remodel project.
The project included 12,780 SF of cut to size pattern flooring, seven different custom designed medallions, thirty radius steps, numerous marble columns and stone countertops. Superior began work at 3 am in the morning and demobilized eight hours later. When we were off the job, it was not apparent that construction was proceeding at all. Superior completed the entire project in less than six weeks.